| Project Location: | Various Streets |
| Project Status: | Complete |
| Bid Opening Date: | January 28, 2025 |
| Mandatory Pre Bid Meeting: | No |
| Construction Start Date: | April 28, 2025 |
| Construction Completion Date: | May, 2025 |
| Contractor: | Corrective Asphalt Materials, LLC |
| Construction Engineer: | In House |
| Design Engineer: | In House |
| Awarded Construction Amount: | $130,000 |
| Adjusted Final Construction Amount: | $120,145.60 |
| Funding Source(s): | Local |
Objective: To slow the natural deterioration of the Village's new asphalt streets.
Description: A rejuvenating agent is applied to the surface of newly paved asphalt streets, and then sand is placed on top of it to prevent tracking of the material.
5/9/25 Update - After a few rain delays, the contractor completed our annual pavement preventative maintenance project this week. A rejuvenating agent was applied to the pavement surface to help extend the life of the pavement.